May 2025

  • Phase 1 | Preview layout, house is on the market

  • Phase 2 | Electrical furniture installation

  • Phase 3 | Indoor MEP system in progress, Exterior wall in progress

  • Phase 4 | Frame construction of the second and third floors

March 2025

  • Phase 1 | Interior decoration is basically completed: kitchen and bathroom furniture & appliances, staircase flooring

  • Phase 2 | Interior decoration in progress, Flooring finished with bathroom tiles, Outdoor concrete road

  • Phase 3 | Third floor frame construction

  • Phase 4 | Foundation pouring completed

January 2025

  • Phase 1 | Bath Tile, Exterior Painting

  • Phase 2 | Interior painting, Drywall Taping

  • Phase 3 | Foundation concrete, 1st Floor Framing

  • Phase 4 | foundation excavation

February 2025

  • Phase 1 | Indoor floor, door, cabinet and countertop installation completed

  • Phase 2 | Bathroom Tile Finish, Floor installation preparation completed

  • Phase 3 | The first floor frame is completed, The second floor frame is completed

  • Phase 4 | Underground pipeline and foundation formwork completed

December 2024

  • Phase 1 | Interior Painting

  • Phase 2 | Insulation, Drywall and Taping

  • Phase 2 | Exterior Wall

  • Phase 3 | Foundation

November 2024

  • Phase 1 | Insulation, Drywall & Taping

  • Phase 2 | MEP

  • Phase 3 | Foundation Work

October2024

  • Phase 1 | Roof paper, Exterior Wall

  • Phase 2 | Window, MEP

  • Phase 3 | Foundation Work

September 2024

  • Phase 1 | Roof, WIndow, MEP

  • Phase 2 | Truss, Roof

August 2024

  • Phase 1 | 2nd & 3rd Framing, Stairs

  • Phase 2 | 1st & 2nd Floor Framing

July 2024

  • Phase 1 | Foundation, 1st Floor Framing

  • Phase 2 | Foundation

June 2024

  • Plumbing of Water, Gas & Electric finish

  • Telephone and cable TV line, Network Cable Connection

  • Backfill & Foundation start

May 2024

  • Off-site Utility Plumbing

  • Excavation of Gutters

  • Plumbing in process

April 2024

  • Block Wall finish

  • Sewer Connection

  • Rainwater Harvesting System

  • Off-site Electric Connection

March 2024

  • Block Wall in process

  • Sewer in process

  • Work stoppages due to heavy rainfall

February 2024

  • Excavation of Utility Trench

  • Preparation

April 2025

  • Phase 1 | Temporary power, Cleaning, side walk, landscaping and parking lot

  • Phase 2 | Kitchen and bathroom, side walk, landscaping and parking lot

  • Phase 3 | Truss & Roof, MEP in process, Scaffolding

  • Phase 4 | 1st floor framing