

May 2025
-
Phase 1 | Preview layout, house is on the market
-
Phase 2 | Electrical furniture installation
-
Phase 3 | Indoor MEP system in progress, Exterior wall in progress
-
Phase 4 | Frame construction of the second and third floors

March 2025
-
Phase 1 | Interior decoration is basically completed: kitchen and bathroom furniture & appliances, staircase flooring
-
Phase 2 | Interior decoration in progress, Flooring finished with bathroom tiles, Outdoor concrete road
-
Phase 3 | Third floor frame construction
-
Phase 4 | Foundation pouring completed

January 2025
-
Phase 1 | Bath Tile, Exterior Painting
-
Phase 2 | Interior painting, Drywall Taping
-
Phase 3 | Foundation concrete, 1st Floor Framing
-
Phase 4 | foundation excavation

February 2025
-
Phase 1 | Indoor floor, door, cabinet and countertop installation completed
-
Phase 2 | Bathroom Tile Finish, Floor installation preparation completed
-
Phase 3 | The first floor frame is completed, The second floor frame is completed
-
Phase 4 | Underground pipeline and foundation formwork completed


December 2024
-
Phase 1 | Interior Painting
-
Phase 2 | Insulation, Drywall and Taping
-
Phase 2 | Exterior Wall
-
Phase 3 | Foundation
November 2024
-
Phase 1 | Insulation, Drywall & Taping
-
Phase 2 | MEP
-
Phase 3 | Foundation Work

October2024
-
Phase 1 | Roof paper, Exterior Wall
-
Phase 2 | Window, MEP
-
Phase 3 | Foundation Work

September 2024
-
Phase 1 | Roof, WIndow, MEP
-
Phase 2 | Truss, Roof
August 2024
-
Phase 1 | 2nd & 3rd Framing, Stairs
-
Phase 2 | 1st & 2nd Floor Framing

July 2024
-
Phase 1 | Foundation, 1st Floor Framing
-
Phase 2 | Foundation

June 2024
-
Plumbing of Water, Gas & Electric finish
-
Telephone and cable TV line, Network Cable Connection
-
Backfill & Foundation start

May 2024
-
Off-site Utility Plumbing
-
Excavation of Gutters
-
Plumbing in process

April 2024
-
Block Wall finish
-
Sewer Connection
-
Rainwater Harvesting System
-
Off-site Electric Connection

March 2024
-
Block Wall in process
-
Sewer in process
-
Work stoppages due to heavy rainfall

February 2024
-
Excavation of Utility Trench
-
Preparation

April 2025
-
Phase 1 | Temporary power, Cleaning, side walk, landscaping and parking lot
-
Phase 2 | Kitchen and bathroom, side walk, landscaping and parking lot
-
Phase 3 | Truss & Roof, MEP in process, Scaffolding
-
Phase 4 | 1st floor framing










































