Living in
Buena Park
With a strong emphasis on education, excellent schools cater to families, while convenient access to major highways ensures easy connectivity to nearby cities and attractions. Proximity to stunning beaches and major metropolitan areas further cements Buena Park as a central hub for both work and play, making it a hidden gem in the heart of Southern California.
Nestled in Southern California, Buena Park seamlessly combines suburban tranquility with a vibrant urban spirit. From the world-renowned Knott's Berry Farm to its historic landmarks like the Whitaker-Jaynes Estate, the city offers a diverse tapestry of entertainment and rich cultural heritage.
Property Address
7692 9th Street, Buena Park, CA 90621
Number of Units
18 Units Townhomes
Unit Living Square Footage
~1,590 SQ.FT
Total Site Area
30,039 SQ.FT
Property Overview
Starting at
$869,999
Mainhouse
1,212 - 1,596 Sq.ft
Available Units
18
Bedrooms
2-3
Bathrooms
3
Garage
508-516 Sq.ft
Gallery

Project Progress
April 2025
-
Phase 1 | Temporary power, Cleaning, side walk, landscaping and parking lot
-
Phase 2 | Kitchen and bathroom, side walk, landscaping and parking lot
-
Phase 3 | Truss & Roof, MEP in process, Scaffolding
-
Phase 4 | 1st floor framing



March 2025
-
Phase 1 | Interior decoration is basically completed: kitchen and bathroom furniture & appliances, staircase flooring
-
Phase 2 | Interior decoration in progress, Flooring finished with bathroom tiles, Outdoor concrete road
-
Phase 3 | Third floor frame construction
-
Phase 4 | Foundation pouring completed
.webp)
.webp)
.webp)
.webp)
February 2025
-
Phase 1 | Indoor floor, door, cabinet and countertop installation completed
-
Phase 2 | Bathroom Tile Finish, Floor installation preparation completed
-
Phase 3 | The first floor frame is completed, The second floor frame is completed
-
Phase 4 | Underground pipeline and foundation formwork completed

.webp)
.webp)
.webp)
January 2025
-
Phase 1 | Bath Tile, Exterior Painting
-
Phase 2 | Interior painting, Drywall Taping
-
Phase 3 | Foundation concrete, 1st Floor Framing
-
Phase 4 | foundation excavation



December 2024
-
Phase 1 | Interior Painting
-
Phase 2 | Insulation, Drywall and Taping
-
Phase 2 | Exterior Wall
-
Phase 3 | Foundation









November 2024
-
Phase 1 | Insulation, Drywall & Taping
-
Phase 2 | MEP
-
Phase 3 | Foundation Work



October
2024
-
Phase 1 | Roof paper, Exterior Wall
-
Phase 2 | Window, MEP
-
Phase 3 | Foundation Work



September 2024
-
Phase 1 | Roof, WIndow, MEP
-
Phase 2 | Truss, Roof



August 2024
-
Phase 1 | 2nd & 3rd Framing, Stairs
-
Phase 2 | 1st & 2nd Floor Framing



July 2024
-
Phase 1 | Foundation, 1st Floor Framing
-
Phase 2 | Foundation



June 2024
-
Plumbing of Water, Gas & Electric finish
-
Telephone and cable TV line, Network Cable Connection
-
Backfill & Foundation start



May 2024
-
Off-site Utility Plumbing
-
Excavation of Gutters
-
Plumbing in process



April 2024
-
Block Wall finish
-
Sewer Connection
-
Rainwater Harvesting System
-
Off-site Electric Connection



March 2024
-
Block Wall in process
-
Sewer in process
-
Work stoppages due to heavy rainfall



February 2024
-
Excavation of Utility Trench
-
Preparation





7682-7692 9th Street, Buena Park, CA 90621
Location
Contact us
This builder reserves the right to change price, design, and specifications without prior notice or obligation. All square footages are approximate only. The floorplans, home elevations, and colors, landscaping and site plans are an artist's depiction. Size, number, and location of windows, front entries, doors, and solar panels may vary per plan and/or elevation. Options may be included at an additional cost and are subject to construction cut-off date. Views vary per homesite location and are not guaranteed and may be altered by subsequent development, construction, and landscaping growth. All imagery is representational and does not depict specific building views, orientation, or future amenity details. Models or photos do not reflect racial preference.
NorCal:(855) ALHOME1 SoCal:(855) ALHOME6
Call
All information is deemed reliable but not guaranteed and should be independently reviewed and verified.
May 2025
-
Phase 1 | Preview layout, house is on the market
-
Phase 2 | Electrical furniture installation
-
Phase 3 | Indoor MEP system in progress, Exterior wall in progress
-
Phase 4 | Frame construction of the second and third floors